< Back to Search

Air Quality State Permit to Operate

State Permit to Operate - Process Equipments

This permit applies to certain processes or equipment that require an initial or temporary Air Quality State Permit to Operate, an amended existing Air Quality State Permit to Operate, or a renewal of an existing Air Quality State Permit to Operate. Before applying for an initial or temporary permit, the applicant should reach out to the Air Quality Permits Program for additional permit to construct requirements.

Expected Fee

$0

Estimated Processing Time

4 Months

  1. Submit completed Form 26 - Application Form For Process Equipment
  2. Submit completed Budget Reconciliation and Financing Act Form

Air and Radiation Administration
Air Quality Permits Program - Permit Services Administrator
[email protected]
(410) 537-3230

Start Application

State Permit to Operate - Incinerators

This permit applies to certain incinerators that require an initial or temporary Air Quality State Permit to Operate, an amended existing Air Quality State Permit to Operate, or a renewal of an existing Air Quality State Permit to Operate. Before applying for an initial or temporary permit, the applicant should reach out to the Air Quality Permits Program for additional permit to construct requirements.

Expected Fee

$0

Estimated Processing Time

4 Months

  1. Submit completed Form 27 - Application Form For Incinerators
  2. Submit completed Budget Reconciliation and Financing Act Form

Air and Radiation Administration
Air Quality Permits Program - Permit Services Administrator
[email protected]
(410) 537-3230

Start Application

State Permit to Operate - Fuel Burning Equipment

This permit applies to certain fuel burning equipment that require an initial or temporary Air Quality State Permit to Operate, an amended existing Air Quality State Permit to Operate, or a renewal of an existing Air Quality State Permit to Operate. Before applying for an initial or temporary permit, the applicant should reach out to the Air Quality Permits Program for additional permit to construct requirements.

Expected Fee

$0

Estimated Processing Time

4 Months

  1. Submit completed Form 28 - Application Form For Fuel Burning Equipment
  2. Submit completed Budget Reconciliation and Financing Act Form

Air and Radiation Administration
Air Quality Permits Program - Permit Services Administrator
[email protected]
(410) 537-3230

Start Application