Air Quality General Permit to Construct
Vehicle Refinishing Autobody - General Permit to Construct
Expected Fee
$500 for the facility
Estimated Processing Time
45 Days
-
Submit the Complete Request for Coverage: Application for Vehicle Refinishing
-
Submit Initial Notification and Compliance Notification forms
Air and Radiation Administration
Air Quality Permits Program -
Permit Services Administrator
[email protected]
(410) 537-3230
Small Motor Vehicle Refueling Facilities - General Permit to Construct
Expected Fee
$200 for the facility
Estimated Processing Time
45 Days
-
Submit the Complete Request for Coverage: Application for Small Motor Vehicle Refueling Facilities
Air and Radiation Administration
Air Quality Permits Program -
Permit Services Administrator
[email protected]
(410) 537-3230
Medium Motor Vehicle Refueling Facilities - General Permit to Construct
Expected Fee
$200 for the facility
Estimated Processing Time
45 Days
-
Submit the Complete Request for Coverage: Application for Medium Motor Vehicle Refueling Facilities
Air and Radiation Administration
Air Quality Permits Program -
Permit Services Administrator
[email protected]
(410) 537-3230
Large Motor Vehicle Refueling Facilities - General Permit to Construct
Expected Fee
$200 for the facility
Estimated Processing Time
45 Days
-
Submit the Complete Request for Coverage: Application for Large Motor Vehicle Refueling Facilities
Air and Radiation Administration
Air Quality Permits Program -
Permit Services Administrator
[email protected]
(410) 537-3230
Charbroilers and Pit Barbecues - General Permit to Construct
Expected Fee
$100 per unit
Estimated Processing Time
45 Days
-
Submit the Complete Request for Coverage: Application for Charbroilers and Pit Barbecues
Air and Radiation Administration
Air Quality Permits Program -
Permit Services Administrator
[email protected]
(410) 537-3230
Groundwater Air Strippers & Soil Vapor Extraction - General Permit to Construct
Expected Fee
$250 per system
Estimated Processing Time
45 Days
-
Submit the Complete Request for Coverage: Application for Groundwater Air Strippers & Soil Vapor Extraction
Air and Radiation Administration
Air Quality Permits Program -
Permit Services Administrator
[email protected]
(410) 537-3230
Perchlorethylene (PERC) Dry Cleaning Equipment - General Permit to Construct
Expected Fee
$500 per piece of equipment
Estimated Processing Time
45 Days
-
Submit the Complete Request for Coverage: Application for Perchlorethylene (PERC) Dry Cleaning Equipment
Air and Radiation Administration
Air Quality Permits Program -
Permit Services Administrator
[email protected]
(410) 537-3230
Small Fuel Burning (Boiler/Heater) Equipment - General Permit to Construct
Expected Fee
$400 per piece of equipment
Estimated Processing Time
45 Days
-
Submit the Complete Request for Coverage: Application for Small Fuel Burning (Boiler/Heater) Equipment
Air and Radiation Administration
Air Quality Permits Program -
Permit Services Administrator
[email protected]
(410) 537-3230
Medium Fuel Burning (Boiler/Heater) Equipment - General Permit to Construct
Expected Fee
$500 per piece of equipment
Estimated Processing Time
45 Days
-
Submit the Complete Request for Coverage: Application for Medium Fuel Burning (Boiler/Heater) Equipment
Air and Radiation Administration
Air Quality Permits Program -
Permit Services Administrator
[email protected]
(410) 537-3230
Non-Heatset Sheet-fed Offset Lithographic Printing - General Permit to Construct
Expected Fee
$500 per piece of equipment
Estimated Processing Time
45 Days
-
Submit the Complete Request for Coverage: Application for Non-Heatset Sheet-fed Offset Lithographic Printing
Air and Radiation Administration
Air Quality Permits Program -
Permit Services Administrator
[email protected]
(410) 537-3230
Concrete Batch Plant - General Permit to Construct
Expected Fee
$250 for the plant
Estimated Processing Time
45 Days
-
Submit the Complete Request for Coverage: Application for Concrete Batch Plant
Air and Radiation Administration
Air Quality Permits Program -
Permit Services Administrator
[email protected]
(410) 537-3230
Off-Road Gasoline Refueling Facilities - General Permit to Construct
Expected Fee
$200 for the facility
Estimated Processing Time
45 Days
-
Submit the Complete Request for Coverage: Application for Off-Road Gasoline Refueling Facilities
Air and Radiation Administration
Air Quality Permits Program -
Permit Services Administrator
[email protected]
(410) 537-3230
Emergency Generators - General Permit to Construct
Expected Fee
$400 per generator set
Estimated Processing Time
45 Days
-
Submit the Complete Request for Coverage: Application for Emergency Generators
-
Submit Engine Manufacturer Literature/Engine Specification Sheet
-
Copy of the engine Certificate of Conformity or other evidence showing that the engine is certified to meet U.S.. EPA Tier standards for emergency engines if the electric generator set is NOT an existing unit constructed before June 12, 2006
Air and Radiation Administration
Air Quality Permits Program -
Permit Services Administrator
[email protected]
(410) 537-3230